Skip to main content

Latest Updates

Update on footpath link to Windsor Road

As stated at the most recent Public Meeting, construction on the footpath link from Darwin Green to Windsor Road is progressing well and the footpath is still scheduled to be opened on 6th October 2023, providing a beneficial connection for residents between Darwin Green and the local area.

Read more

Update following the Darwin Green Public Meeting

Barratt was grateful for the opportunity to provide any update on works taking place at Darwin Green as well as to discuss the proposed demolition plans at the second Public Meeting held on 4th September 2023.

Read more

Next public Meeting

We are pleased to confirm that the next public meeting will take place on Monday 4th September between 7pm-9:30pm at Storey’s Field Centre, Eddington Avenue, Cambridge, CB3 1AA.

Read more

Latest works section

Following the opening of community facilities on site, please see an update below in regard to current works taking place to help deliver these facilities.

Read more

Frequently Asked Questions

Following the public meeting on the 29th June 2023 and email communication over recent weeks we wanted to set out answers to the most common questions here.

Read more

Update from John Dillon, Regional Director

Thank you for the opportunity to meet with residents affected by our Darwin Green Development at the public meeting on the 29th June.

Read more

Update following the Darwin Green Public Meeting

Barratt was grateful for the opportunity to discuss the foundation design issues at Phase Two and other issues experienced by residents living on Darwin Green at the Public Meeting held on 29th June 2023.

Read more

Update on Phase Two Foundations

Following the discovery of issues with the design of some of the foundations of the first homes under construction on Phase Two at Darwin Green, Barratt David Wilson appointed a second independent engineer to conduct a further review of the foundation designs at Phase One in order to provide added reassurance for homeowners.

Read more

Phase Two Foundations

Barratt David Wilson's extensive quality assurance processes discovered issues with the design of some of the foundations of the first homes that are currently under construction on Phase Two at Darwin Green 1.

Read more